History
-
1981
-
Jan. 21Launched Nosa Labor-Management Council
-
Feb. 18Completed Pohang Steel Mill Phase 4
-
Feb. 28Transitioned from state-invested enterprise to state-financed enterprise
-
Nov. 4Gwangyangman Bay was selected as the site for the second steelworks
-
-
1980
-
Jun. 30Entered into an agreement for joint development of Green Hills Mine in Canada
-
-
1979
-
Dec. 6Formed the Business Enhancement Committee
-
-
1978
-
Oct. 30Selected as a builder and operator of second steel mill
-
Dec. 8Completed construction of Pohang Steel Mill Phase 3
-
-
1977
-
Jan. 1Launched R&D Center
-
Apr. 30Made the first shipment of cold-rolled products
-
-
1976
-
May 31Completed construction of Pohang Steel Mill Phase 2
-
Nov. 16Established Steel Education Foundation
-
-
1974
-
Oct. 1Blew in foundry blast furnace
-
Dec. 30Passed the U$100 million mark in steel exports and the ₩100 billion mark in revenues
-
-
1973
-
Mar. 2Received first shipment of coking coal
-
Jun. 9Tapped the first batch of molten iron from Pohang Steelworks Blast Furnace No.1 at 7:30am
-
Jul. 3Completed Pohang Steel Mill Phase 1
-
-
1972
-
May 1Built a pier for product delivery
-
Jul. 4Completed construction of Heavy Plate Plant No.1 at Pohang Steelworks (first loading on July 31)
-
Dec. 31Relocated headquarters to Pohang and opened an office in Seoul
-
-
1971
-
Jan. 27Established Steel Scholarship Foundation
-
Apr. 1Removed credential-based job titling
-
Apr. 8Founded in-house newsletter Soetmul (molten iron) (- December 15, 1997)
-
Aug. 20To meet schedule, historical first emergency model was issued to speed up Hot Rolling Plant construction
-
Nov. 25Concluded the company's first long-term iron ore offtake agreement with Hamersley
-